PranaryCDF Delivery Intelligence
PPS

Education

Thorn Park Primary 1x3 Classroom Block

Kabulonga, Lusaka Central, Lusaka Province.

Thorn Park Primary 1x3 Classroom Block-15.4332, 28.2843
Project timeline
  1. Planned
  2. Procured
  3. In Progress
  4. 4Completed

Started on site

20 Aug 2025

Last field verification

20 Mar 2026

Completed & handed over

20 Mar 2026
Constituency disbursements
TrancheDateAmountStatus
2026 Tranche 215 Apr 2026K14,000,000
Disbursed
2026 Tranche 124 Jan 2026K12,000,000
Disbursed
2026 Tranche 3Jun–Jul 2026K14,000,000
Pending
Budget
Spent100%

Allocated

K1,050,000

Spent to date

K1,050,000

Remaining

K0
Contractor

Chalimbana Contractors

Average delivery

Registration

PACRA-778294

TPIN

1560426224

Active projects

9

Completion rate

44%
Location

Constituency

Ward

Kabulonga

Province

GPS

-15.4332, 28.2843
View location