Health
Wusakile Health Post Construction
Mindolo, Nkana, Copperbelt Province.
Back to constituency
In Progress
Wusakile Health Post Construction-12.8603, 28.1642
Project timeline
- Planned
- Procured
- 3In Progress
- 4Completed
Started on site
9 Dec 2025
Last field verification
12 Apr 2026
Completed & handed over
—
Constituency disbursements
| Tranche | Date | Amount | Status |
|---|---|---|---|
| 2026 Tranche 2 | 7 Apr 2026 | K14,000,000 | Disbursed |
| 2026 Tranche 1 | 17 Jan 2026 | K12,000,000 | Disbursed |
| 2026 Tranche 3 | Jun–Jul 2026 | K14,000,000 | Pending |
Budget
Spent124%
Allocated
K1,700,000
Spent to date
K2,110,000
Remaining
K-410K
Contractor
Kafue Roads and Bridges
Poor delivery
Registration
PACRA-278180
TPIN
1192929358
Active projects
4
Completion rate
25%
Location