Water & Sanitation
Limulunga Ward Borehole Drilling
Kabula, Lukulu, Western Province.
Back to constituency
In Progress
Field verification pending
Limulunga Ward Borehole Drilling-14.4186, 23.2796
Project timeline
- Planned
- Procured
- 3In Progress
- 4Completed
Started on site
22 Jun 2025
Last field verification
Field verification pending
Completed & handed over
—
Constituency disbursements
| Tranche | Date | Amount | Status |
|---|---|---|---|
| 2026 Tranche 2 | 3 Mar 2026 | K14,000,000 | Disbursed |
| 2026 Tranche 1 | 23 Jan 2026 | K12,000,000 | Disbursed |
| 2026 Tranche 3 | Jun–Jul 2026 | K14,000,000 | Pending |
Budget
Spent38%
Allocated
K320,000
Spent to date
K120,000
Remaining
K200K
Contractor
Kalahari Civil Group
Poor delivery
Registration
PACRA-829502
TPIN
1790752285
Active projects
6
Completion rate
0%
Location