PranaryCDF Delivery Intelligence
PPS

Water & Sanitation

Bauleni Water Reticulation (planned follow-on)

Bauleni, Lusaka Central, Lusaka Province.

Field verification pending
Bauleni Water Reticulation (planned follow-on)
Project timeline
  1. 1Planned
  2. 2Procured
  3. 3In Progress
  4. 4Completed

Started on site

Last field verification

Field verification pending

Completed & handed over

Constituency disbursements
TrancheDateAmountStatus
2026 Tranche 215 Apr 2026K14,000,000
Disbursed
2026 Tranche 124 Jan 2026K12,000,000
Disbursed
2026 Tranche 3Jun–Jul 2026K14,000,000
Pending
Budget
Spent0%

Allocated

K280,000

Spent to date

K0

Remaining

K280K
Contractor

No contractor procured yet — project is still in planning.

Location

Constituency

Ward

Bauleni

Province

GPS